Friday, September 20, 2019

Elizabeth construction / Elijah builders / ELJ Konstract Cebu Experience


I’m writing this blog to help potential home investors in preventing what my family went (or am) going through regarding a supposed home builder in Cebu, Philippines. 

My wife and I recently bought a piece of property on Mactan island, Cebu.  We wanted to place a house in it and we needed a builder.  So, like in all modern ways, we searched the internet for a builder.  I’m not sure why, but at the time, there didn’t seem like a lot of builders with a web presence.  Unfortunately for us, we came upon the website elizabethconstruction.ph or elizabethdesignbuild.com (links may no longer work). They were well developed sites, lots of pictures of houses/buildings of their projects, their services offered with “quality and affordable construction”. It was essentially a "We have a solution to all your needs!"  website.  So we gave them a call and was in contact with a person named Jerzon Cesnorio Figueroa, owner/manager of Elizabeth construction.   He first asked about the property documents, then a survey as expected from any builder.  We asked about building permits and he said they can get it done, as part of the contract, during the building process. 


Conceptual
Month 1

After a few weeks of designing and budgeting, we had an agreed contract signed for a 10 month build time, completed by end of 2018.  We were on our way to a new house…or so we thought.



Month 2
After prepping and a few weeks with builder onsite, the wife, who was periodically checking, was questioning some of the building practices and rate of progress.  Workers generally didn’t have power tools and materials was constantly scarce.  Even the foreman was complaining for lack of materials.  I, assuming certain tasks could be slow at times or some engineering reason, told her to just to keep monitoring.  In our contract, we stipulated progress payment plan.  Jerzon, each month, asked for payment, which was a fixed amount.  However, nothing in terms of a written progress report was presented. We just paid each month which was a big mistake.


Month 3
During the months under the contract, we saw our initial foreman/engineer quit.   We kept asking about progress on the building permits, and Jerzon said he’ll get it done next week, etc.  Of course it didn’t.  At about 8-9th month of the contract, the wife, after much effort on her side, we finally got the permits in place.  The experience regarding permits was it took tooth and nail to get this builder to do anything.  One of the things we complained about was workers were leaving the site to attend to other projects.  We apparently were low priority.  We even paid early with the hope of speeding up construction.  By month 10, our side of the contract was fulfilled, all payments except a final payment upon turnover.

Month 5

Month 6: 2nd Floor
By the end of contract, Jerzon formally asked for a 3-month extension.  We gave it to him, even though there was no apparent reason.  We had him sign a form to stipulate final payment would decrease each month after the extension.  At this time, the house was up but there was still no roof. Workers were putting up ceiling and interior stuff.  No Roof!  When no workers were around, there was always at least one worker just painting, almost like there just to seem like work was progressing.

Month 12: Beyond end of contract. 
Does this look anywhere near complete?
Month 10



The 3-month extension goes by (Month 14), Jerzon asks for another 3-month extension (to Month 17).   We brought in a lawyer with demand letter to finish up in the 2nd 3-month extension. During this extension, more substandard work occurs and painting to cover it up.  Tin underlayer roof installed but leaky.  No engineer or management for the workers so they just did what they wanted.
Month 15 Interior
Month 15 Exterior
















Month 17 Rear
House by Elijah Builders Seven Months after Contract Turnover Date
Month 17 Front

By the end of the 2nd extension, we hired a lawyer with demand letter for a meeting.  We also had a structural engineer assess the building and found out the inadequacy of the house should there be an earthquake/typhoon.  Further, concrete roof tiles was planned and paid for in the beginning, thus adding a lot of potential weight to the house that somehow management overlooked during construction.  
Improper Truss Anchoring
Honey comb on Concrete


"Quality and Affordable Construction?"

During the meeting with the lawyer, we presented the structural integrity of the house with Jerzon.  He had the arrogance to question the engineering assessment so he hired another structural engineer and received similar results.  The house needed rectification…on a new construction project!  If it was designed and constructed correctly, rectification wouldn’t be required. Understanding his work was inadequate and incomplete, an undertaking agreement was signed by Jerzon for another 4 months.  This time it would involve an engineer hired by us to manage/report Jerzon.  So all that Jerzon needed to do was deliver materials and workers.  Afterwards, Jerzon contracted out a roofer and had more trusses installed for the roof to support the cement roof tiles.  That took about a week.  After that, there was just a painter covering up evidence, basically not doing anything relevant.  By the end of the month, we had another demand letter presented if he was going to continue the project and get real work done. After another month and with no response, project was considered abandoned.   So that was the last grace period.

We now have a lawsuit submitted to this builder and person for breach of contract “Article 1167. If a person obliged to do something fails to do it, the same shall be executed at his cost. This same rule shall be observed if he does it in contravention of the tenor of the obligation. Furthermore, it may be decreed that what has been poorly done be undone.”  With three extensions offered past contract date and outside engineer assessments on quality and 50% complete at best, I wonder what possible excuse he could conjure up in court.

So where did we go wrong?

We certainly didn’t do enough research.  For one, Jerzon is just a mechanical engineer as noted in the Philippines Professional Regulation Commission (PRC).  What does a mechanical engineer know about civil engineering work?  Further, the business was not licensed Philippine Contractors Accreditation Board (PCAB), see here.

Do you want to deal with this nightmare construction company?
We should have demanded written progress reports before payment and hired another engineer to spot check for quality earlier on.  Of course we did not know this builder would prove to be incompetent and had no real intentions of completing the contract in any reasonable time. Or was that the plan?







Aftermath:

In the weeks that followed, we hired another builder, reviewing the next contract more carefully and also documenting the house before reconstruction began.

Elizabeth construction has been renamed to Elijah Builders, Elijah Builders and Development Corp, or ELJ Konstract I wonder why.  Too much negative feedback about the prior business name or trying to hide from his obligations?  Several other victimized clients have also been discovered so an estafa case is building. Would you like to join this case?

If you like or learned something about this story, be sure to spread the word (or link), so other hard working people don't fall for this bad construction company.

8 comments:

Dennis Rosos said...

Hello. Im sorry about your experience with the construction in Cebu. This might be not a good timing but I will take this opportunity to introduce my company A.R. Kitchen Cabinet Design that provide i terior fit out cabinets. For more info you can visit my official website www.arkitchencabinet.com or fb page www.facebook.com/modularcabinetcebu

Thank you

Dennis Rosos
Sales and Operation
A.R. Kitchen Cabinet Design
09177721690
09338556537
dennis@arkitchencabinet.com

Elizabeth construction/ Elijah builders Cebu Experience said...

I had the same experienced with this bastard Jerzon Fegueroa, i entered into a contract on building what is supposed to be called as "My Dream House" but that dream house became a nightmare because of this scumbag man.

I signed a contract on Oct 10, 2016 and paid 2.5M as a down payment that supposed to be a 10 months contract but it took them almost 2 years and abandoned after that because he doesn't have anything to get from me anymore. I paid 95% of contract price and they only had 60% progress of the construction.

I don't have any experience about construction. What I want is just to save some money as an OFW and build my dream house. I was so scared about him abandoning my project so every time he asks for payment I religiously pay without fail.

This Jerzon, give me lots of stress and sleepless nights and its not only me but it includes my parents as they were the one looking after the project. It was a nightmare.

I paid an engineer to survey the progress and here is what he told me:


Hi Dixie,
I was able to visit your project with your parents yesterday.
In my opinion, the project will not be delivered to you satisfactorily by March because only 2-3 workers are assigned there, and as per your parents, these workers are not supplied with enough materials to finish the job. I have observed the same pattern with the other projects previously, and one time I visited one project in Mactan and the owner's sister had similar problems and complains - rain water seeping thru walls and roofs, haphazard finishes, unsettled modification requests, etc. Similar problems observed in the Liloan project, even in Corona del Mar in Talisay.
I could not provide a detailed reporting because of the possible legal implications it may bring, but I can share with you insights and advise on how to effectively deal with this.
The project as I saw it is merely on the structural phase - the finishes are completely lacking, electrical works are not yet completed, painting is stuck in first coating, waterproofing was not executed effectively, the roofing is haphazardly done, tiles are not protected, etc. In total, the construction progress does not correspond to the amount you've already paid.
You may proceed with your legal pursuit against him, just to put it in the court records, and to possibly force him to deliver through a court order, but based on my experience, he will can defend this with project computations and counter complains to possibly make you look as if you are the one at fault. The same thing happened to my church community sister whom I referred to him. Fortunately, the Bible promises to humble those who seek to be exulted today.
In the construction industry, as long as there is no accident resulting in death or injury, the contractor can be safe since all other complaints will just fall within the "civil case" realm which can be countered by legal delays and empty promises.
I believe a better way to deal with people such as the one you've encountered now, is through that platform which he feared most - social media and the internet - since that is currently his primary source of new victims. He can always delete your comments posted in the various social media pages he own, but no one can prevent you from creating your own page specifically exposing a certain company. You can even create your own page titled with such company. There is a page and even a website out there with the sole purpose of raising complaints about a certain brand to create awareness for people - e.g. http://dell-hell.blogspot.com/ ; http://www.carcomplaints.com/BMW/ ; https://www.facebook.com/groups/556288597758485/

I apologize for selling him to you... If only I've known him earlier...

The engineer who sent me this was his old so called partner...

I feel sorry for us! we need to do something to make this devil go to jail! NO DEMAND LETTERS WILL SCARE JERZON FEGUEROA!

Gracie Ong said...

I was also scammed by this Jerzon. Can we file our demand letters altogether?

Meerconsultants said...

Thanks a for providing the best blog post.This is very helpful and knowledgable.
Construction company in Islamabad

Unknown said...

Had a very similar experience as the persons above where we had to change contractor, jerzon is a crook, he has always been and always will be untrustworthy. You will have seen him arrive to meet you in in his sports motorcycle and Audi car.
I also should have done more research and stuck to my no payment ahead of work completed. In the end I changed at the right time and found a much better contractor.

Unknown said...

JACCS BUILDER SCAMMER
We engaged with Jeffrey Figueroa who happens to be a sibling of Jerson. He has a company named JACCS BUILDER. https://www.jaccsbuilder.com. The same thing happened to us. Our house project in Camotes was abandoned and left hanging after he was able to collect 70% of the total contract price. As per assessment of our architect, he only accomplished 30% based on the Project Plan. Later did we learn that Jeffrey Figueroa is the operations manager of Elizabeth Construction.

Anonymous said...

Not with Jerson nor JACCS but different bogus contractor- paid everything and they just left. His name is Recolito Tac-al and his company Isometric. He is a crook- beware of this guy.

Anonymous said...

Who did u end up hiring to finish your house? Can u reccomend them?